Sample: entirely fictitious example, not a client case.

Based on BSI Standard 200-4 and ISO 22301. Professional assessment, not legal advice.

1 Framework

Company
Mid-sized regional gas distribution operator with distribution network, network control centre, emergency repair standby, depot and administration.
Period
Disruptions of up to 30 days are considered.
Damage limit
Damage is no longer tolerable from [threshold set by management].
Stage
Starting as a reactive BCMS under BSI Standard 200-4, securing the time-critical processes first.
Link to NIS2
As an operator of a gas distribution network, the company falls under Annex 1 No. 1.4.1 BSIG. For network operation, Sec. 28(5) BSIG applies the rules of Sec. 5c to 5e of the German EnWG instead of, among others, Sec. 30, 32 and 38 BSIG. Business continuity, recovery after an emergency and crisis management are among the requirements there too (Sec. 5c(4) No. 3 EnWG), and management must implement and oversee them (Sec. 5e(1) EnWG).

2 Same disruption, different moment

How bad a disruption is often depends less on how long it lasts than on when it happens. That is why we ask not only what fails, but also when it hurts.

BusinessBad momentQuiet moment
Flower shopValentine's Day. Every hour without till or cooling costs sales that no other day brings back.An ordinary Tuesday. The customers will come back tomorrow.
Restaurant kitchenSaturday evening, every table taken. After a few minutes the guests are waiting and the evening is lost.Mid-morning, no guests in the house. The technician comes in peace, nobody notices anything.
Delivery serviceThe run-up to Christmas. Without route planning the parcels stay put, and every day of backlog keeps growing.A quiet day in January. The routes can be run by hand.
Waste collectorHeatwave, the organic waste bins are out on the street, and dispatch has failed.A cool week and a day without collection. The rounds can be caught up.

These businesses are only illustrations. The sample follows a regional gas distribution operator.

3 Time-critical processes

A process is time-critical if its disruption within the period considered can cause intolerable damage. Each process is assessed for its worst moment. The moment is recorded in the report so that decisions in an emergency can follow the actual situation.

ProcessWorst momentQuiet momentResponse
Fault reporting and repairtime-criticalAny time. If someone reports a smell of gas, the fault line must be reachable and someone must respond.There is none.Around the clock, within minutes
Network control centre and remote monitoringtime-criticalCold spell in January. Demand is high, pressure and volumes must be watched continuously.Summer night with little demand. On-site checks are enough for a few hours.Within minutes in winter, within hours in summer
Network plans for construction sitestime-criticalPeak civil engineering season. Excavators wait for network plans or dig without current information.Frost and hardly any construction sites. A few days hardly show.Within one working day in the construction season
Market communication and billingtime-criticalShortly before a market communication deadline.Between deadlines, the data can be caught up.Within days, faster before deadlines
Payrollnot time-criticalThe day before the payment run, salaries risk being late.Mid-month, there is plenty of time.Days. In an emergency, an advance based on the previous month

Processes needed by time-critical processes are time-critical as well. That is why the systems behind them follow in the next section.

4 Systems, backup and recovery

SystemFindingSignificance
Fault hotlineRuns over the same phone system as the administration.If the phone system fails, the most important process cannot be reached.
Network control systemRecovery lies with the manufacturer.Procedure and duration are not agreed with the manufacturer.
Geographic information system with network plansDaily backup, restore never fully tested.The standby team has no current set of plans without the network.
ERP and market communicationOperated by a service provider.No agreed recovery ahead of deadlines.

5 Gaps and measures

Immediately

  • Make the fault hotline reachable by a second route.
  • Test a full restore of the geographic information system once and record the duration, [measured duration].
  • Check whether a backup is kept disconnected from the network.

Over the coming months

  • Agree the recovery of the network control system with the manufacturer.
  • Provide a current set of plans for the standby team without the network.
  • Set reinforced standby for the control centre and IT only for the heating season. This lowers the effort without weakening protection.

Organisation

  • Appoint an emergency organisation with decision-makers and deputies.
  • Set up a communication channel that works without email and the phone system.

Deliberately later

  • A full BCMS under ISO 22301 only once the time-critical processes are reliably secured.

6 Open points

  • [Threshold set by management] to be defined.
  • Set maximum disruption times per process and moment in hours with the process owners.
  • Set the minimum operating level of the network control centre with network management.
  • Dependence on service providers and manufacturers not yet assessed.

7 Next steps

  1. Set up a second route for the fault hotline and rehearse the switchover once.
  2. Carry out and evaluate the restore test of the geographic information system.
  3. Agree the recovery of the network control system with the manufacturer.
  4. Appoint the emergency organisation and rehearse the alerting once.
  5. Update the result yearly before the heating season and after every exercise or major change.

Reservation

This sample is a professional assessment and not legal advice. It is based on BSI Standard 200-4 and ISO 22301, and for the link to NIS2 on the German BSI Act as in force from 6 December 2025 and the German EnWG, checked on 7 November 2026. The technical rules of gas supply are not covered by this sample. Values in square brackets appear in the real report as results of the assessment.

Sample: entirely fictitious example, not a client case.